IDA Parkmore East (Phase 2)

This project involved the Construction of an Access Road within the IDA Business Park Located in Parkmore, Galway City.

Works included:

  • Clearance of the site.
  • Excavation & disposal of 2,500m3 of material
  • Imported Clause 804
  • Construction of the carriageway.
  • Installation of Drainage (Foul & Surface)
  • Construction of Kerbing, Footpaths & Paving
  • Road Markings
  • Signage
  • Hard and soft Landscaping
  • Installation of a public lighting system.
  • Installation of all services (water, sewerage, electricity, telecoms and public lighting).
  • Construction of an electrical substation
  • Construction of a foul pumping station.
  • Supply, installation, and commissioning of pumping equipment.
  • Client IDA Ireland
  • Location Galway
  • Completed Jun-11