The project comprised of the construction of 250m of new road pavement, the construction of a 32m diameter roundabout, the construction of a 56 space car park and the upgrade of 200m of existing road and fooptaths.
The works included the following:
- Realignment of existing road and reconstruction of new sections, planing and resurfacing of the entire scheme including tie-ins to all interconnecting roads and streets.
- New footpath, shared surfaces and parking areas.
- Raising all service covers in the carriageway.
- Resurfacing of the existing carriageway and construction of new carriageway where appropriate.
- Splitter island build-outs at roundabout.
- Construction of 2 No. uncontrolled Pedestrian Crossing including all signage, lining and tactile paving.
- New road markings and traffic signs and relocation of existing signage.
- Traffic management throughout the works.
- New drainage gullies and tie-ins to existing drainage system.

![Lidl_Stiftung_&_Co._KG_logo.svg[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/Lidl_Stiftung__Co._KG_logo.svg1-Logo.jpg)


![Waterford-City-and-County-Council-logo[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/Waterford-City-and-County-Council-logo1-Logo.jpg)

![South-Tipperary-County-Council[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/South-Tipperary-County-Council1-Logo.jpg)
![1664[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/16641-Logo.jpg)
![4011249-CAVAN%20COUNTY%20COUNCIL%20.1[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/4011249-CAVAN20COUNTY20COUNCIL20.11-Logo.jpg)
![city-council[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/city-council1-Logo.jpg)

![enercon[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/enercon1-Logo.jpg)
![ida_logo[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/ida_logo1-Logo.jpg)
![LibertyInsurance2[1] – Logo](https://www.nrsgroup.eu/wp-content/uploads/2015/12/LibertyInsurance21-Logo.jpg)